Neville Hall

Project duration – 52 weeks

Project value – £150k

Client – Brims Construction

 

Neville Hall was built in the 1870s as a country house and is a Grade II Listed Building.

Working with Brims Construction, we designed and built numerous bespoke scaffolds on the Grade II listed building, Neville Hall, in Newcastle City Centre.

One of the scaffold designs was an access lifting beam trolley system around the core and access to roof areas to allow for glazing to be completed with a NIKO rail system. The rail system allowed the glass to be transported around the scaffold safely and securely.

The neighbouring building provided access restrictions due to an overhang, the scaffold design was amended and re-erected to step under and round the overhang in less than 48 hours.

 