Langley First School
Contractor – North Tyneside Council
Project Location – Whitley Bay
Project Duration – 10 weeks
When working with North Tyneside Council, we produced a bespoke scaffold design to enable roofing work to take place. We designed and produced a rolling roof to provide a fall protection system whilst roofing works were being carried out. This roofing system is faster to install and is a more efficient way to complete progressive works as it prevents the need to re-erect and dismantle continuously. The rolling roof system also provides fall protection and allows for seamless project delivery as the scaffold is only removed the once, upon full completion of the project.